Metal products & Machinery

Reduce service costs by capacity improvement

BUSINESS CONTEXT

  • No. 1 automotive cabling plant of our client.
  • Highly competitive business environment.
  • Service and lowest cost price critical to stay in business.

CUSTOMER NEED

  • In 2010 significant additional rush shipments and outsourcing costs due to capacity limitations in one of their key production lines.

RESULTS

  • In 2011 OEE improved from 43 % to 69 % (61 % improvement).
  • Outsourcing and service costs were avoided, resulting in a 2.5 m Euro cost savings vs 2010.

CHANGES

  • Operational discipline to work accordingly.
  • Daily leadership, connected to shop floor defects.
  • Non-value-added work eliminated in key machine set ups.
  • Good X-functional teamwork.

R&G APPROACH

  • Detailed operating standards defined and implemented.
  • Daily IDEX to drive execution according standard.
  • Rigorous SMED to improve set up times.
  • Training of management and improvement team.

CLIENT TESTIMONIAL

“Fast execution of ideas and improvements. Operators and employees see directly that something is changing positively”

Site Manager